While we love building commercial swimming pools from scratch, often what’s required is a major refurbishment of existing facilities. After an inspection of Urrbrae Agricultural College’s 25 metre outdoor pool, Statewide Pools presented a proposal for works which was accepted by the College.

The Urrbrae Pool’s gutters were removed and replaced with a wet deck system on both sides. These measures enhanced the pool’s aesthetics and helped with the conservation of water. Tiles then needed replacing along the pool sides and in other areas where years of wear and tear had taken their toll.

We removed the up-stand on both sides of the pool to provide a wet deck edge. ‘Concrete cancer spots’ were then treated by exposing the reo bars and treating them with appropriate products. Once again, tiles had to be replaced for this work to be completed.

Our stainless steel department then fabricated new ladders, expansion joints were resealed, existing starting blocks were replaced with convenient portable starting blocks and with the addition of new lane ropes, Urrbrae’s $110 000 pool upgrade was complete.

View the PDF factsheet for this project

 

Pool with the old concrete starting blocks to be replaced with removable starting blocks

Pool prior to renovation – scum gutter to be cut & replaced with new wet deck, tiling & stainless steel ladders

Newly renovated wet deck & new stainless steel ladder

Renovated scum gutter to wet deck

Completed swimming pool

 

We have a team of Qualified Project Managers in charge of all Construction including OH &S. We comply with the National Code of Construction. Our Supervisors ensure delivery of Quality Assured Products.